Thanks to Commissioner Gimenez’ staff for forwarding along this update on the Commodore bike trail from Esther Calas, P.E., Director, Miami-Dade Public Works Department, along with the renderings below of the new proposed bridge crossing at Cocoplum Circle.
The Commodore trail is a continuous, primarily off-road bicycle/pedestrian facility within the designated Bike Route 1 which parallels the following corridors within the limits of the City of Miami:
- Douglas Road to Main Highway
- Main Highway to McFarlane Road
- McFarlane Road to South Bayshore Drive
- South Bayshore Drive to Aviation Avenue
The project consists of reconstructing portions of the trail to meet current design standards by providing a 10’ bikepaths and minimum of 6’ grass strip separating the path from the travel lanes. This is a minimum width for a paved two-way path minimizing the risk of bicycle-bicycle and bicycle-pedestrian collisions, and absolute minimum width of clear zone from the edge of the travel lane for local roads without curb & gutter.
However, there are segments of the trail where the existing path does not meet design standards because of insufficient right-of-way, presence of existing coral walls or in order to preserve big banyan trees. These areas, where the minimum path width and the minimum width of clear zone cannot be provided are considered exception areas. Therefore, the scope of work for these substandard portions of the shared use path includes only resurfacing of the bikepath. Additionally, in these exception areas, warning signs will be installed advising that the bikeway narrows. Furthermore, “No Parking/Bikepath” signs will be installed to avoid people parking on the existing trail. Finally, the bikepath will be identified with appropriate signage throughout the limits of the project.
The pedestrian/bicycle path will increase the efficiency of cycling as a mode of transportation, will reduce traffic congestion on existing roads and will provide recreational opportunity for Miami-Dade residents and visitors.
The project is in its final design stage. Pending are permit approvals from the environmental agencies for the proposed pedestrian bridge over Coral Gables Waterway along with execution of temporary construction easements by the City of Coral Gables. The project is expected to be bid for construction in October 2010 and construction is expected to start in November 2010.
LISTEN TO THE LATEST TALKING HEADWAYS PODCAST
Find us on Facebook
Recent Comments
- Anonymous on FDOT District 4 Bicycle/Pedestrian Coordinator
- Mike Arias on Friday Funny: The TIGER Grant
- Mike Lintro on City of Miami Public Hearing: Small Building Parking Exemption
- Anonymous on Follow Tri-Rail on Twitter
- Anonymous on Follow Tri-Rail on Twitter
- Anonymous on Follow Tri-Rail on Twitter
Subscribe via Email
Recent Activity
Tags
Bicycle Bicycle Infrastructure bicycles bike lanes Bike Miami Days Bikes bikeway biking Brickell bus Calendar Climate Change Coconut Grove complete streets Congestion Cycling Downtown Miami Downtown Miami FDOT MDT Metromover Metrorail Miami Miami-Dade County Miami-Dade Transit Miami 21 Miami Beach Miami Dade Parking Parks Pedestrian Pedestrian Activity Pedestrians Pic o' the Day Public Transit Rickenbacker Causeway Sprawl Streetcar Traffic Transit Transit Oriented Development Transportation Tri-Rail Uncategorized Urban Planning